Estimated cost per square metre is €8708 (not €6500)

The Oireachtas Public Accounts Committee on the 31st January 2019, and the Health Committee (16th January 2019) were given the breakdown by the NPHDB of the €1.7 billion expected cost (as of January 2019) of completing the project :

Total Construction cost €1,093,800,000, with the non construction costs bringing the total Building cost to €1,433,000,000. Other costs managed by Children’s Health Ireland of €293,000,000 gave a final total cost [as of 31.01.2019] of €1,700,000,000.

Cost per sq metre : This is the construction cost per metre of gross internal area. The Ambulatory /Urgent Care Centres : – €60million (cost of the two AUCCs inc VAT) of the total construction cost . Cost per sqm of AUCCs is €5586.

Main Hospital at St. James’s : – The remaining €1,033,800,000 of the Total Construction Cost is the construction cost of the main hospital. Gross internal area is 119,368sq m. Using figures supplied by the NPHDB as of 16. 01.2019 to the Health Committee and 31.01.2019 to the Public Accounts Committee,the New Children’s Hospital Alliance estimates that the cost per sq m is €8708 (not €6,500 as claimed by the NPHDB). This will further increase if construction inflation rises (as is anticipated) above 4% as from July 2019 . Other costs-VAT, design changes etc which are outwith the GMP (Guaranteed maximum price) are also expected .

It would appear that the NPHDB chose to include the area of the car park as part of the gross internal area, contrary to estimates for international comparator hospitals – thus falsely lowering the cost per sq. metre. The AECOM international comparator hospital document lists the most expensive hospital as being €8000 per msq. The Dublin NCH is the most expensive of all the hospitals studied.

Hospital Board issue incorrect “Key Facts”- 320, not 380, ensuite rooms

Eilish Hardiman, CEO, issued a letter to Children’s Hospital staff, 16th January 2019, after meeting the Oireachtas Health Committee. Please note that a “key fact” included is incorrect. There are not “380 individual, ensuite inpatient bedrooms, each with a bed for parent”. There are, as per Bord Pleanála planning permission, 320 (not 380) en suite individual bedrooms

There are major question marks over the accuracy of many “key facts” issued by the Children’s Hospital Group Board. Truth would be helpful- and deserved by the Irish public.

NCHA Submission to Joint Health Committee

On Wednesday last,16th January 2019, members of the New Children’s Hospital Alliance and the ExtraSpecial Kids group were present in the public gallery to hear Tom Costello, Chair NPHDB, John Pollock, Project Director NPHDB and Eilish Hardiman, CEO and Emma Curtis, Medical Director, Children’s Hospital Group being questioned by committee members regarding the out-of-control costs of the NCH project at St James’s.

Go ahead given to BAM April 2017 despite Cost and Medical concerns

2nd February 2017 – BAM states that the company had been notified that it is the preferred bidder for the NCH construction contract.

There is no DoH statement on the matter but Minister for Finance , Paschal Donohoe,states on RTE One’s ‘Morning Ireland’ that the process is ongoing and that a ‘business case’ was yet to be presented to him to make a decision on. He will be working with Minister Harris on this.

13th February – A letter is sent to all members of the Cabinet from the Connolly for Kids Hospital Group including the New Children’s Hospital Alliance(NCHA) and the Jack and Jill Foundation requesting that certain questions be answered on Cost and other matters before the contract is approved by cabinet.

6th March 2017 – Minister of Health, Simon Harris, is tasked by Cabinet with answering the questions in that letter “directly and with urgency” but despite repeated requests by the Government Chief Whip, Regina Doherty, no reply to the letter is received from the Minister – this is the Minister who prides himself in demanding “democratic accountability”

24th April 2017 – Minister for Health Simon Harris presents a formal memo to Cabinet . Cabinet approves the Definitive Business Case, including the full project cost.

3rd August 2017 – BAM signs the Construction Contract



Functions of the NPHDB and CHGB

The functions of the NPHDB, as outlined in S.I. 246 of 2007, are:

  • to plan, design, build, furnish and equip a national paediatric hospital (‘the new children’s hospital’) in accordance with a brief approved by the Health Services Executive (“the HSE”) with the prior consent of the Minister, and subject to any subsequent variations to this brief as may be determined by the HSE in consultation with the NPHDB, and with the prior consent of the Minister; and
  • do any other thing as is necessary for the performance of its functions.

The other functions of the NPHDB are currently undertaken by the Children’s Hospital Group Board (CHGB). These functions are as follows:

  • in consultation with the relevant hospitals, prepare plans for the transfer of services from the relevant hospitals to the hospital;
  • in consultation with the relevant hospitals, prepare a human resource strategy for the transfer to the new children’s hospital; and
  • explore the possibility of securing philanthropic contributions to meet all or part of the capital cost of developing the hospital, and foster the philanthropic interests that already exist in relation to the provision of paediatric services.

Responsibility for these functions passed to the CHGB on the13th September 2013, as set out in an operational agreement between the NPHDB, the CHGB and the HSE and approved by the Department of Health.

Costs that Connolly and St. James’s submitted to Dolphin 2012

 

 See below -the  costing estimate for the NPH by St.James (inner urban, brownfield) was less than that of Connolly  hospital (M50, greenfield) -strange!

The NATIONAL PAEDIATRIC HOSPITAL INDEPENDENT REVIEW , commissioned by James Reilly,Minister for Health, PART ONE : FINANCIAL ANALYSIS, July 2011 gives  €650m as the budget for the NPH at the MATER site .

Connolly Hospital submission of NPH Construction Cost ,May 2012, to the Dolphin Group :-

FOI-ConnollyHealthCampus

St. James’s Hospital submission of Construction Cost,( May 2012) to the Dolphin group :-

Building cost NPH,Maternity 2012